It’s not the technology – it’s the org chart

November 22, 2026

The news continues to come in. Stories of companies that are close to completing their facilities but unable to make it over the finish line and into commercial production. Certainly, there are funding and financial issues. But let’s take a deeper dive into some of the commercial and technical aspects of facility construction.

Building is hard. It’s even more difficult if you’re a startup team. Large companies have dedicated project management and construction teams for their capital projects. As a startup, you’re trying to do it on a shoestring budget, perhaps with one person who is also balancing other responsibilities. Where can things go wrong? It all starts with your home team.

Among other things, you can outsource design and engineering, procurement, and construction. But you cannot outsource responsibility. No one cares as much about your project as you do. Yes, you should absolutely bring in experts when it comes to engineering and construction. But who is watching the experts? You can’t toss your idea and contract over the wall and expect to come back 18 months later to a completed facility without being involved. The right level of owner involvement and oversight makes the difference between a project that comes in on time and on budget, and one that blows both.

At this point, you may be nodding your head while simultaneously wondering: How do I do this? Especially with a first-of-a-kind process, you need both process and execution expertise at the table. No one knows your process as well as you do, so make sure you have adequate technical support that understands the nuances of what you’re trying to produce and how. This must be balanced with someone who has actually built facilities before (ideally many of them), someone who understands which modifications make production easier without affecting your outcome, what equipment or construction methods can save time and money, and how contract structures and contractor incentives play out over an 18-month build.

I’ve seen this gap sink otherwise promising projects. A startup hires a brilliant process engineer to own the technical side, brings in an engineering firm, and assumes the EPC contract will handle the rest. Eighteen months later, they’re six months behind schedule and 40% over budget – not because the process didn’t work, but because no one on their side understood contractor incentives well enough to catch change orders before they compounded, or knew that a design decision made in month two would create a procurement bottleneck in month 10.

The startups that make it to commercial production aren’t the ones with the best process or the biggest budget. They’re the ones who knew they couldn’t do it alone

This pattern shows up too frequently with startups building in the US$10-100 million range. The imbalance usually runs in one direction: too much emphasis on process knowledge and too little on execution experience. One of the refrains I hear repeatedly from founders is, ‘But I need someone who knows my process’. Yes, absolutely – but that isn’t mutually exclusive with someone who has actually built facilities before.

How do we bridge this gap? It’s relatively easy for well-connected startups to find someone with deep experience in their specific process. The dilemma is on the execution side. The process expert rarely has broad experience building facilities. And someone who’s built dozens of plants may not be willing to take a startup’s risk for a startup’s salary.

The argument that you need this capability in-house, full time, is flawed. Strategic use of outside – but independent – experts on a fractional basis can give you the best of both worlds. You gain industry expertise from people who have lived through dozens of successes and failures, allowing them to replicate what works and avoid what doesn’t. If you’re evaluating a fractional advisor, ask direct questions. How many facilities have you built at this scale? What’s the most expensive mistake you’ve seen founders make at this stage? Can you point to a project where you overruled the technical preference for a commercial reason, and why? Good answers separate people who’ve actually lived through a build from those who simply sound like they have.

Both technical and commercial experience are critical. Technically, the process has to work. From an execution standpoint, the facility has to be built on time, on budget, and to specification. Make sure you have people on your side who cover both, and recognize that keeping these roles distinct spreads your risk and improves your odds.

The startups that make it to commercial production aren’t the ones with the best process or the biggest budget. They’re the ones who knew they couldn’t do it alone and got the right kind of help before the concrete was poured.

David Ziskind is Managing Partner at Mach Global Advisors. He helps companies planning for or have recently secured Series A or B funding to launch emerging or first-of-a-kind projects successfully. This article is republished from the Q2 2026 edition of Protein Production Technology International, the industry's leading resource for alternative proteins. To subscribe to all future editions, please click here

‍

If you have any questions or would like to get in touch with us, please email info@futureofproteinproduction.com

About the Speaker

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

By clicking “Accept All Cookies”, you agree to the storing of cookies on your device to enhance site navigation, analyze site usage, and assist in our marketing efforts. View our Privacy Policy for more information.