Scaling at the speed of reality: Matching facility ambitions to market readiness

April 28, 2026

The dream is seductive: build a world-scale facility, demonstrate commitment to investors, capture market share before competitors arrive, and ride the wave of consumer demand to profitability. It is a narrative that has driven many food-tech companies to break ground on massive manufacturing facilities. Lately, we have seen what happens when that dream collides with market reality.

The challenge is not ambition – we need ambitious goals to transform our food system. The challenge is timing. Building large-scale infrastructure before demand materializes creates a dangerous mismatch. Companies are effectively betting millions of dollars that consumers will embrace their product at the scale and speed their facility requires. That is not a calculated risk – it is a gamble with runway.

This pattern has repeated itself: a company secures funding, designs an impressive facility and commits to construction. Eighteen months later, the market has not developed as projected. Consumer adoption may be slower than expected, a key retail partnership may fall through, or the regulatory environment may shift. Whatever the reason, the result is the same: a facility designed for 100x capacity operating at 5x demand. The unit economics that looked promising at full capacity become impossible to sustain.

Building large-scale infrastructure before demand materializes creates a dangerous mismatch – it is a gamble with runway

So, how can this trap be avoided? It starts with asking the right questions before committing capital. What evidence is there of sustained demand? Not pilot programs or test markets, but actual repeated purchasing behavior. Are consumers buying a product a second, third or tenth time? Or is there trial without retention?

Next, companies must examine their technology readiness honestly. Is the process truly fixed, or are adjustments still being made? Every process change after construction begins multiplies costs exponentially. If optimization is still ongoing, the business is not ready to scale – regardless of investor or board expectations. That said, initial planning can still begin to clarify design decisions and potential facility costs.

The competitive landscape also requires careful consideration. First-mover advantage matters in some markets, but in food, quality and economics often matter more. Building first but building incorrectly does not create a defensible advantage. In many cases, being second or third – with lower costs and better quality – wins the market. This is more nuanced for first-of-a-kind (FOAK) technologies. While the first mover may not succeed commercially, its role remains critical: it generates the learnings that enable others to scale manufacturing more effectively.

There are smarter approaches. Rather than committing to a single mega-facility, companies can pursue modular expansion. Starting with a commercial-scale line allows processes and economics to be proven before scaling further. Facilities and utilities can then be designed to accommodate future expansion without major reconstruction. While per-unit costs may be higher initially, the company avoids risking its entire runway on untested assumptions.

Brownfield opportunities also deserve greater attention. An existing food facility – even one requiring significant modification – can offer a faster, lower-cost path to production than a greenfield build. Existing utilities, permits and workforce capabilities can save both time and capital.

Hybrid manufacturing strategies present another option. A company might retain control of its core process – its key intellectual property – while outsourcing downstream processing or packaging. This approach maintains quality and flexibility as the market develops, with the option to bring more operations in-house once demand justifies the investment.

The reality is that aligning facility ambitions with market readiness requires patience in an industry that often rewards bold, early action. But bold action without validation is not courage – it is recklessness. The companies that succeed will scale deliberately, aligning facility investment with real market signals rather than projections and assumptions.

Building infrastructure is expensive and time-consuming. Building the wrong infrastructure at the wrong time can be fatal. In today’s capital-constrained environment, the margin for error is slim. The priority must be to understand the market, prove demand, and scale at the speed of reality – not the speed of ambition.

David Ziskind is Managing Partner at Mach Global Advisors. He helps companies planning for or have recently secured Series A or B funding to launch emerging or first-of-a-kind projects successfully. This article is republished from the Q1 2026 edition of Protein Production Technology International, the industry's leading resource for alternative proteins. To subscribe to all future editions, please click here

If you have any questions or would like to get in touch with us, please email info@futureofproteinproduction.com

About the Speaker

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

By clicking “Accept All Cookies”, you agree to the storing of cookies on your device to enhance site navigation, analyze site usage, and assist in our marketing efforts. View our Privacy Policy for more information.